![]() 157
Tabel 5.23 Tabel Master Production Schedule Dust Collector 20m³
Item No
: 2
Description
:
Dust Collector 20 m³
Lead time
: 1
Safety Stock
:
0
On hand
: 0
Demand Time Fences
:
4
Planning Time Fences
:
10
Period
Past
due
1
2
3
4
5
6
7
8
9
10
11
12
13
14
Forecast
3
18
18
18
18
0
16
24
24
21
18
18
18
15
Actual Order
0
12
15
15
14
0
0
16
20
22
15
15
18
12
Project Available Balance
0
18
24
27
30
12
28
36
36
33
29
29
29
26
11
Available to Promise
0
18
24
27
30
16
32
56
64
65
61
64
67
64
52
Cumulative ATP
18
42
69
99
115
147
203
267
332
393
457
524
588
640
Master Scheduled
18
18
18
18
0
16
24
24
21
18
18
18
15
0
KPT
4
24
24
24
24
0
16
24
24
24
24
24
24
20
?
Perhitungan
-
Project Available Balance (PAB)
PAB
t=DTF
= PAB
t-1
+ MS
t
-
AO
t
.
PAB
DTF=t=PTF
= PAB
t-1
+
MS
t
-
AO
t
atau F
t
(pilih yang paling besar).
-
Available To Promise (ATP)
ATP = ATP
t-1
+ MS
t
-
Actual Order sampai pada periode yang sudah
dijadwalkan pada Master Scheduled.
|