193
Planned Order Receipt = 60
Planned Order Release = 60
PAB21 = (PAB1)1 + (Planned Order Receipt)1
=
9,57 + 60
=
69,57
9
Periode 2
Gross Requirements = 16,468 Kg
Scheduled Receipts = 0
PAB12 = (PAB2)1 (Gross Requirements)2 + (Scheduled Receipts)2
=
69,57 16,468 + 0
=
53,102
Planned Order Receipt = 0
Planned Order Release = 0
(PAB2)2 = (PAB1)2 + (Planned Order Receipt)2
=
53,102 + 0
=
53,102
Perhitungan biayanya :
Biaya Pesan = 2 x Rp 5000,- = Rp 10.000 ,-
Biaya Simpan = Jumlah PAB 2 selama periode x Rp 62 ,25
=
309,572 x Rp 62,25 = Rp 19.270 ,86
Total Biaya = Biaya Pesan + Biaya Simpan = Rp 29.270 ,86
Ternyata
setelah
dilakukan
perhitungan biaya,
teknik
lotting
EOQdan
POQ
memberikan perhitungan biaya
yang paling
minimum. Oleh karena
itu
maka
digunakan
teknik lotting EOQ dalam perhitungan MRP garam.
|